County Commission Meeting
Ordinance 2026-01 (data center rules) was tabled Aug 18th - It has not passed. It can come back.
- NextEra presented a 500MW battery project. The county's zoning ordinance does not address battery storage at all.
- 765kv Line setback is being drafted. Couny rance 850-1,000'. Residents asked for 2,000' and many of us think that is not far enough.